住宅项目开发报建、报批程序
- 文档部分内容预览:
- 住宅项目开发报建报批程序
一、对取得土地和准备开发项目打可行性研究报告和立项申请,然后到计划发展委员会申请立项。
二、凭土地出让合同到规划局规划技术处申报,有规划测绘队测绘后,取得建设项目规划红线图。
三、将总体规划方案报规划局规划管理处审批,通过后领取建设用地规划许可证。
四、总体规划通过后如果一次规划分批实施,就将分期实施的详细规划和相应的单体建筑设计报规划局规划管理处审批。
五、在四阶段审批期间,将各规费收缴部门缴费流转审批完毕,其中包括消防、建设、教育地方配套、卫生防疫、白蚁防止、绿化、人防、墙体改造、散装水泥、城建档案、工程质监等。具体手续办理如下:
1、将报批的范围内的所有建筑单体图纸报当地消防部门进行消防审查,取得建筑工程消防意见
````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````````....
-